— Project Summary

Queue ID
Duke-919551
Capacity
40 MW
Technology
Solar
Status
active
Location
Lincoln, NC
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarDukeLBNL

40 MW generation in Lincoln, NC · In queue since September 2023

40 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Facility Study

IA Status

Interconnection Timeline

Total Duration

2y 6m

Facilities Study50%
Queue EntrySep 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Lincoln

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Mull

Data Source

LBNL

No news available for this project.