— Project Summary

Queue ID
Duke-919393
Capacity
100 MW
Technology
Solar
Status
active
Location
Wake, NC
Region
Southeast
Developer
Duke Energy Progress, LLC
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

100 MW generation in Wake, NC · In queue since September 2023

100 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

2y 6m

Impact Study25%
Queue EntrySep 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Wake

Region

Southeast

Developer

Duke Energy Progress, LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

HARRIS PLANT - WAKE 230KV

Data Source

LBNL