— Project Summary

Queue ID
Duke-899581
Capacity
20 MW
Technology
Gas
Status
active
Location
Wayne, NC
Region
Southeast
Developer
Duke Energy Progress, LLC
IA Status
Cluster Study

BetaActiveGasDukeLBNL

20 MW generation in Wayne, NC · In queue since June 2023

20 MW

Capacity

1

Components

Gas

2y 9m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

2y 9m

Impact Study25%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Wayne

Region

Southeast

Developer

Duke Energy Progress, LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Lee Substation 115 kV

Data Source

LBNL