— Project Summary

Queue ID
Duke-899053
Capacity
120 MW
Technology
Battery
Status
active
Location
Wilkes, NC
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveBatteryDukeLBNL

120 MW storage in Wilkes, NC · In queue since June 2023

120 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Status

Interconnection Timeline

Total Duration

2y 9m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Wilkes

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Wilkes Tie

Data Source

LBNL