BetaActiveBatteryDukeLBNL
199.9 MW storage in Robeson, NC · In queue since June 2023
199.9 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
2y 9m
Impact Study25%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Robeson
Region
Southeast
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Weatherspoon Plant Station
Data Source
LBNL
No news available for this project.