BetaActiveDieselDukeLBNL
2 MW generation in Wake, NC · In queue since June 2023 · Proposed COD November 2025
2 MW
Capacity
1
Components
Diesel
2y 9m
In Queue
Construction
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
5 months past proposed COD
In Study38%
Queue EntryJun 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-06
Project Details
State
NC
County
Wake
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Data Source
LBNL
No news available for this project.