— Project Summary

Queue ID
Duke-897777
Capacity
2 MW
Technology
Other
Status
active
Location
Wake, NC
Region
Southeast
Developer
IA Status
Construction

BetaActiveDieselDukeLBNL

2 MW generation in Wake, NC · In queue since June 2023 · Proposed COD November 2025

2 MW

Capacity

1

Components

Diesel

2y 9m

In Queue

Construction

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 5m

Schedule

5 months past proposed COD

In Study38%
Queue EntryJun 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-06

Project Details

State

NC

County

Wake

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Data Source

LBNL

No news available for this project.