— Project Summary

Queue ID
Duke-897773
Capacity
10 MW
Technology
Other
Status
active
Location
Johnston, NC
Region
Southeast
Developer
IA Status
Construction

BetaActiveDieselDukeLBNL

10 MW generation in Johnston, NC · In queue since June 2023 · Proposed COD May 2026

10 MW

Capacity

1

Components

Diesel

2y 9m

In Queue

Construction

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 11m

In Study38%
Queue EntryJun 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-01

Project Details

State

NC

County

Johnston

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Glen Laurel Industrial 230 kV Substation

Data Source

LBNL

No news available for this project.