2.8 MW generation in Cleveland, NC · In queue since January 2000
2.8 MW
Capacity
1
Components
Other
26y 2m
In Queue
Construction
IA Status
Interconnection Timeline
Total Duration
26y 2m
In Study38%
Queue EntryJan 1, 2000
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined