BetaActiveBatteryDukeLBNL
3.55 MW storage in Vance, NC · In queue since June 2023
3.55 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
2y 9m
Impact Study25%
Queue EntryJun 5, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Vance
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Data Source
LBNL
No news available for this project.