3 MW generation in Marion, FL · In queue since October 2007 · Proposed COD August 2008
3 MW
Capacity
1
Components
Other
18y 5m
In Queue
IA Executed
IA Status
COD target: 2008
Interconnection Timeline
Total Duration
10 months
Schedule
214 months past proposed COD
Construction75%
Queue EntryOct 9, 2007
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2008-08-15
Project Details
State
FL
County
Marion
Region
Southeast
Developer
G2 Landfill
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Maricamp Substation
Data Source
LBNL