— Project Summary

Queue ID
Duke-72
Capacity
340 MW
Technology
Other
Status
active
Location
Osceola, FL
Region
Southeast
Developer
GenOn
IA Status
IA Executed

BetaActiveOtherDukeLBNL

340 MW generation in Osceola, FL · In queue since October 2007 · Proposed COD December 2009

340 MW

Capacity

1

Components

Other

18y 5m

In Queue

IA Executed

IA Status

COD target: 2009

Interconnection Timeline

Total Duration

2y 2m

Schedule

199 months past proposed COD

Construction75%
Queue EntryOct 7, 2007

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2009-12-01

Project Details

State

FL

County

Osceola

Region

Southeast

Developer

GenOn

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Holopaw Substation

Data Source

LBNL

No news available for this project.