340 MW generation in Osceola, FL · In queue since October 2007 · Proposed COD December 2009
340 MW
Capacity
1
Components
Other
18y 5m
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
2y 2m
Schedule
199 months past proposed COD
Construction75%
Queue EntryOct 7, 2007
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-12-01
Project Details
State
FL
County
Osceola
Region
Southeast
Developer
GenOn
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Holopaw Substation
Data Source
LBNL
No news available for this project.