20 MW generation in Richmond, NC · In queue since January 2020 · Proposed COD December 2024
20 MW
Capacity
1
Components
Gas
6y 2m
In Queue
Operational
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 11m
Schedule
15 months past proposed COD
Pre-Study100%
Queue EntryJan 20, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
NC
County
Richmond
Region
Southeast
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Richmond 230 kV
Data Source
LBNL