— Project Summary

Queue ID
Duke-58
Capacity
10 MW
Technology
Other
Status
active
Location
Polk, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
IA Executed

BetaActiveOtherDukeLBNL

10 MW generation in Polk, FL · In queue since January 2007 · Proposed COD May 2008

10 MW

Capacity

1

Components

Other

19y 2m

In Queue

IA Executed

IA Status

COD target: 2008

Interconnection Timeline

Total Duration

1y 4m

Schedule

218 months past proposed COD

Construction75%
Queue EntryJan 17, 2007

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2008-05-01

Project Details

State

FL

County

Polk

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Tiger Bay Substation

Data Source

LBNL

No news available for this project.