— Project Summary

Queue ID
Duke-572280
Capacity
72 MW
Technology
Solar
Status
active
Location
Greenwood, SC
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveSolarDukeLBNL

72 MW generation in Greenwood, SC · In queue since June 2022

72 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Pending

IA Status

Interconnection Timeline

Total Duration

3y 9m

In Study38%
Queue EntryJun 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Greenwood

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Champion Bl 100 kV

Data Source

LBNL

No news available for this project.