BetaActiveSolarDukeLBNL
80 MW generation in Wayne, NC · In queue since June 2022 · Proposed COD August 2026
80 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 2m
Construction75%
Queue EntryJun 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-15
Project Details
State
NC
County
Wayne
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
LEE SUBSTATION - MT OLIVE 230KV
Data Source
LBNL
No news available for this project.