— Project Summary

Queue ID
Duke-569632
Capacity
80 MW
Technology
Solar
Status
active
Location
Scotland, NC
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarDukeLBNL

80 MW generation in Scotland, NC · In queue since June 2022 · Proposed COD August 2026

80 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 2m

Construction75%
Queue EntryJun 27, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-08-19

Project Details

State

NC

County

Scotland

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

FAYETTEVILLE - ROCKINGHAM 230KV

Data Source

LBNL

No news available for this project.