— Project Summary

Queue ID
Duke-569164
Capacity
70.7 MW
Technology
Solar
Status
active
Location
Newberry, SC
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarDukeLBNL

70.7 MW generation in Newberry, SC · In queue since June 2022 · Proposed COD December 2027

70.7 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 6m

Construction75%
Queue EntryJun 24, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

SC

County

Newberry

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Champion Bl 100 kV

Data Source

LBNL

No news available for this project.