— Project Summary

Queue ID
Duke-568986
Capacity
80 MW
Technology
Solar
Status
active
Location
Person, NC
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarDukeLBNL

80 MW generation in Person, NC · In queue since June 2022 · Proposed COD February 2027

80 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 8m

Construction75%
Queue EntryJun 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-02-16

Project Details

State

NC

County

Person

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

ROXBORO PLANT - AEP EAST DANVILLE 230KV

Data Source

LBNL

No news available for this project.