— Project Summary

Queue ID
Duke-568892
Capacity
76 MW
Technology
Solar
Status
active
Location
Darlington, SC
Region
Southeast
Developer
Duke Energy Progress, LLC
IA Status
IA Executed

BetaActiveSolarDukeLBNL

76 MW generation in Darlington, SC · In queue since June 2022 · Proposed COD December 2027

76 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 6m

Construction75%
Queue EntryJun 24, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

SC

County

Darlington

Region

Southeast

Developer

Duke Energy Progress, LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Darlington County Plant Substation

Data Source

LBNL