BetaActiveBatteryDukeLBNL
8 MW storage in Horry, SC · In queue since June 2022 · Proposed COD June 2027
8 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Construction
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryJun 22, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
SC
County
Horry
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Marion Bypass 115KV
Data Source
LBNL
No news available for this project.