— Project Summary

Queue ID
Duke-566542
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Darlington, SC
Region
Southeast
Developer
IA Status
Construction

BetaActiveSolarDukeLBNL

74.9 MW generation in Darlington, SC · In queue since June 2022 · Proposed COD December 2026

74.9 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Construction

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 6m

In Study38%
Queue EntryJun 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

SC

County

Darlington

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

DOVESVILLE NUCOR 230KV TAP LINE

Data Source

LBNL

No news available for this project.