BetaActiveSolarDukeLBNL
74.9 MW generation in Darlington, SC · In queue since June 2022 · Proposed COD December 2026
74.9 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Construction
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 6m
In Study38%
Queue EntryJun 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
SC
County
Darlington
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
DOVESVILLE NUCOR 230KV TAP LINE
Data Source
LBNL
No news available for this project.