— Project Summary

Queue ID
Duke-566202
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Anderson, SC
Region
Southeast
Developer
IA Status
IA Pending

BetaActiveSolarDukeLBNL

74.9 MW generation in Anderson, SC · In queue since June 2022 · Proposed COD March 2031

74.9 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Pending

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

8y 9m

In Study38%
Queue EntryJun 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-03-07

Project Details

State

SC

County

Anderson

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Toxaway 100 kV

Data Source

LBNL

No news available for this project.