— Project Summary

Queue ID
Duke-566170
Capacity
56 MW
Technology
Battery
Status
active
Location
Wake, NC
Region
Southeast
Developer
Duke Energy Progress, LLC
IA Status
IA Executed

BetaActiveBatteryDukeLBNL

56 MW storage in Wake, NC · In queue since June 2022 · Proposed COD December 2026

56 MW

Capacity

1

Components

Battery

3y 9m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 6m

Construction75%
Queue EntryJun 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

NC

County

Wake

Region

Southeast

Developer

Duke Energy Progress, LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

NEW HILL 230KV TAP LINE

Data Source

LBNL