— Project Summary

Queue ID
Duke-565080
Capacity
75 MW
Technology
Solar
Status
active
Location
Darlington, SC
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarDukeLBNL

75 MW generation in Darlington, SC · In queue since June 2022

75 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

3y 9m

Construction75%
Queue EntryJun 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Darlington

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

ROBINSON PLANT - ROCKINGHAM 230KV

Data Source

LBNL

No news available for this project.