— Project Summary

Queue ID
Duke-563202
Capacity
2.667 MW
Technology
Battery
Status
active
Location
Burke, NC
Region
Southeast
Developer
IA Status
Construction

BetaActiveBatteryDukeLBNL

2.667 MW storage in Burke, NC · In queue since June 2022 · Proposed COD September 2025

2.667 MW

Capacity

1

Components

Battery

3y 9m

In Queue

Construction

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 3m

Schedule

6 months past proposed COD

In Study38%
Queue EntryJun 1, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-15

Project Details

State

NC

County

Burke

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

Nebo Ret

Data Source

LBNL

No news available for this project.