BetaActiveBatteryDukeLBNL
4.6 MW storage in Fairfield, SC · In queue since June 2022 · Proposed COD September 2025
4.6 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Construction
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
6 months past proposed COD
In Study38%
Queue EntryJun 1, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-15
Project Details
State
SC
County
Fairfield
Region
Southeast
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Point of Interconnection
Longtown Ret
Data Source
LBNL
No news available for this project.