— Project Summary

Queue ID
Duke-5
Capacity
480 MW
Technology
Gas
Status
active
Location
Pasco, FL
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveGasDukeLBNL

480 MW generation in Pasco, FL · In queue since October 1999

480 MW

Capacity

1

Components

Gas

26y 5m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

26y 5m

Construction75%
Queue EntryOct 28, 1999

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

FL

County

Pasco

Region

Southeast

Developer

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Hudson Substation 230 kV

Data Source

LBNL

No news available for this project.