BetaActiveGasDukeLBNL
480 MW generation in Pasco, FL · In queue since October 1999
480 MW
Capacity
1
Components
Gas
26y 5m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
26y 5m
Construction75%
Queue EntryOct 28, 1999
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
FL
County
Pasco
Region
Southeast
Developer
—
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Hudson Substation 230 kV
Data Source
LBNL
No news available for this project.