69.75 MW generation in Chester, SC · In queue since November 2017 · Proposed COD December 2027
69.75 MW
Capacity
1
Components
Solar
8y 4m
In Queue
Construction
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
10y 1m
In Study38%
Queue EntryNov 21, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
SC
County
Chester
Region
Southeast
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Point of Interconnection
Landsford
Data Source
LBNL
No news available for this project.