BetaActiveOtherDukeLBNL
10 MW generation in Citrus, FL · In queue since December 2006 · Proposed COD May 2009
10 MW
Capacity
1
Components
Other
19y 3m
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
2y 5m
Schedule
206 months past proposed COD
Construction75%
Queue EntryDec 11, 2006
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-05-01
Project Details
State
FL
County
Citrus
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Crystal River Substation
Data Source
LBNL
No news available for this project.