— Project Summary

Queue ID
Duke-44
Capacity
10 MW
Technology
Other
Status
active
Location
Citrus, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
IA Executed

BetaActiveOtherDukeLBNL

10 MW generation in Citrus, FL · In queue since December 2006 · Proposed COD May 2009

10 MW

Capacity

1

Components

Other

19y 3m

In Queue

IA Executed

IA Status

COD target: 2009

Interconnection Timeline

Total Duration

2y 5m

Schedule

206 months past proposed COD

Construction75%
Queue EntryDec 11, 2006

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2009-05-01

Project Details

State

FL

County

Citrus

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Crystal River Substation

Data Source

LBNL