— Project Summary

Queue ID
Duke-43
Capacity
10 MW
Technology
Other
Status
active
Location
Citrus, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
IA Executed

BetaActiveOtherDukeLBNL

10 MW generation in Citrus, FL · In queue since December 2006 · Proposed COD November 2008

10 MW

Capacity

1

Components

Other

19y 3m

In Queue

IA Executed

IA Status

COD target: 2008

Interconnection Timeline

Total Duration

1y 11m

Schedule

212 months past proposed COD

Construction75%
Queue EntryDec 11, 2006

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2008-11-01

Project Details

State

FL

County

Citrus

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Crystal River Substation

Data Source

LBNL

No news available for this project.