BetaActiveBatteryDukeLBNL
100 MW storage in Wake, NC · In queue since June 2019
100 MW
Capacity
1
Components
Battery
6y 9m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
6y 9m
Construction75%
Queue EntryJun 20, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Wake
Region
Southeast
Developer
Knightdale Energy Center, LLC
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Milburnie - Wake 230 kV
Data Source
LBNL
No news available for this project.