BetaActiveGasDukeLBNL
40 MW generation in Polk, FL · In queue since January 2024 · Proposed COD September 2025
40 MW
Capacity
1
Components
Gas
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 8m
Schedule
7 months past proposed COD
Impact Study25%
Queue EntryJan 11, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
FL
County
Polk
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Tiger Bay Substation 230 kV
Data Source
LBNL
No news available for this project.