— Project Summary

Queue ID
Duke-343
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Brevard, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

74.9 MW generation in Brevard, FL · In queue since January 2024 · Proposed COD June 2028

74.9 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 5m

Impact Study25%
Queue EntryJan 10, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

FL

County

Brevard

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

New 230 kV switching station 230 kV

Data Source

LBNL