BetaActiveSolarDukeLBNL
74.9 MW generation in Brevard, FL · In queue since January 2024 · Proposed COD June 2027
74.9 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Impact Study25%
Queue EntryJan 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
FL
County
Brevard
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
New 230 kV switching station 230 kV
Data Source
LBNL