74.9 MW generation in Hamilton, FL · In queue since November 2023 · Proposed COD December 2025
74.9 MW
Capacity
1
Components
Solar
2y 4m
In Queue
IA Pending
IA Status
COD target: 2025
Total Duration
2y 1m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
State
FL
County
Hamilton
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Twin Rivers Switching Station 230 kV
Data Source
LBNL
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC Central Florida-Kathleen Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Duke Energy Florida, LLC DeBary- Winter Springs Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Last updated 2026-03-14