61.2 MW generation in Gilchrist, FL · In queue since September 2023 · Proposed COD June 2028
61.2 MW
Capacity
1
Components
Solar
2y 6m
In Queue
IA Pending
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
In Study38%
Queue EntrySep 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
FL
County
Gilchrist
Region
Southeast
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Bell Tap 69 kV
Data Source
LBNL