84 MW generation in Polk, FL · In queue since July 2023 · Proposed COD May 2025
84 MW
Capacity
1
Components
Gas
2y 8m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
1y 10m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
State
FL
County
Polk
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Hines Substation 230 kV
Data Source
LBNL
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC Central Florida-Kathleen Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Duke Energy Florida, LLC DeBary- Winter Springs Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Last updated 2026-03-14