— Project Summary

Queue ID
Duke-333
Capacity
84 MW
Technology
Gas
Status
active
Location
Polk, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Construction

BetaActiveGasDukeLBNL

84 MW generation in Polk, FL · In queue since July 2023 · Proposed COD May 2025

84 MW

Capacity

1

Components

Gas

2y 8m

In Queue

Construction

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 10m

Schedule

11 months past proposed COD

In Study38%
Queue EntryJul 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-01

Project Details

State

FL

County

Polk

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Hines Substation 230 kV

Data Source

LBNL