BetaActiveOtherDukeLBNL
418 MW generation in Pinellas, FL · In queue since March 2006 · Proposed COD June 2009
418 MW
Capacity
1
Components
Other
20 years
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
3y 3m
Schedule
205 months past proposed COD
Construction75%
Queue EntryMar 6, 2006
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-06-01
Project Details
State
FL
County
Pinellas
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Bartow Substation
Data Source
LBNL
No news available for this project.