74.9 MW generation in Hamilton, FL · In queue since June 2023 · Proposed COD December 2025
74.9 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
State
FL
County
Hamilton
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Suwannee River - Pine Grove (GA PWR) 230 kV
Data Source
LBNL
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC Central Florida-Kathleen Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Duke Energy Florida, LLC DeBary- Winter Springs Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Last updated 2026-03-14