— Project Summary

Queue ID
Duke-327
Capacity
100 MW
Technology
Battery
Status
active
Location
Citrus, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Construction

BetaActiveBatteryDukeLBNL

100 MW storage in Citrus, FL · In queue since May 2023 · Proposed COD March 2027

100 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Construction

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 10m

In Study38%
Queue EntryMay 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

FL

County

Citrus

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Powerline Substation 115 kV

Data Source

LBNL