— Project Summary

Queue ID
Duke-326
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Osceola, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
IA Executed

BetaActiveSolarDukeLBNL

74.9 MW generation in Osceola, FL · In queue since May 2023 · Proposed COD December 2026

74.9 MW

Capacity

1

Components

Solar

2y 10m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 7m

Construction75%
Queue EntryMay 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

FL

County

Osceola

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Whippoorwill Switching Station 230 kV

Data Source

LBNL

No news available for this project.