BetaActiveSolarDukeLBNL
74.9 MW generation in Osceola, FL · In queue since May 2023 · Proposed COD December 2026
74.9 MW
Capacity
1
Components
Solar
2y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 7m
Construction75%
Queue EntryMay 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
FL
County
Osceola
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Whippoorwill Switching Station 230 kV
Data Source
LBNL
No news available for this project.