— Project Summary

Queue ID
Duke-324
Capacity
74.5 MW
Technology
Solar
Status
suspended
Location
Gilchrist, FL
Region
Southeast
Developer
Florida Renewable Partners, LLC
IA Status
Suspended

BetaSuspendedSolarDukeLBNL

74.5 MW generation in Gilchrist, FL · In queue since February 2023 · Proposed COD December 2026

74.5 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 10m

Suspended38%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

FL

County

Gilchrist

Region

Southeast

Developer

Florida Renewable Partners, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Hayfield Substation 230 kV

Data Source

LBNL

No news available for this project.