74.5 MW generation in Gilchrist, FL · In queue since February 2023 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
Suspended38%
Queue EntryFeb 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
FL
County
Gilchrist
Region
Southeast
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Hayfield Substation 230 kV
Data Source
LBNL
No news available for this project.