— Project Summary

Queue ID
Duke-323
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Jefferson, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Construction

BetaActiveSolarDukeLBNL

74.9 MW generation in Jefferson, FL · In queue since February 2023 · Proposed COD June 2027

74.9 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Construction

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntryFeb 13, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

FL

County

Jefferson

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Waukeenah Substation 115 kV

Data Source

LBNL