74.9 MW generation in Hernando, FL · In queue since November 2022 · Proposed COD June 2026
74.9 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 7m
Suspended38%
Queue EntryNov 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
FL
County
Hernando
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Brooksville-Bushnell East 230 kV
Data Source
LBNL
No news available for this project.