BetaActiveBatteryDukeLBNL
8 MW storage in Suwannee, FL · In queue since November 2022 · Proposed COD December 2024
8 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Construction
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 1m
Schedule
15 months past proposed COD
In Study38%
Queue EntryNov 19, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
FL
County
Suwannee
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Suwannee 230 kV Substation 230 kV
Data Source
LBNL
No news available for this project.