— Project Summary

Queue ID
Duke-318
Capacity
8 MW
Technology
Battery
Status
active
Location
Suwannee, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Construction

BetaActiveBatteryDukeLBNL

8 MW storage in Suwannee, FL · In queue since November 2022 · Proposed COD December 2024

8 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Construction

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 1m

Schedule

15 months past proposed COD

In Study38%
Queue EntryNov 19, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

FL

County

Suwannee

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Suwannee 230 kV Substation 230 kV

Data Source

LBNL

No news available for this project.