BetaActiveSolarDukeLBNL
74.5 MW generation in Levy, FL · In queue since August 2022 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Construction
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntryAug 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-30
Project Details
State
FL
County
Levy
Region
Southeast
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Sunset Switching Station 230 kV
Data Source
LBNL
No news available for this project.