— Project Summary

Queue ID
Duke-3
Capacity
297 MW
Technology
Gas
Status
active
Location
Polk, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
IA Executed

BetaActiveGasDukeLBNL

297 MW generation in Polk, FL · In queue since March 1999

297 MW

Capacity

1

Components

Gas

27 years

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

27 years

Construction75%
Queue EntryMar 1, 1999

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

FL

County

Polk

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Intercession City Substation 230 kV

Data Source

LBNL