297 MW generation in Polk, FL · In queue since March 1999
297 MW
Capacity
1
Components
Gas
27 years
In Queue
IA Executed
IA Status
Total Duration
27 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Commercial operation date not yet determined
State
FL
County
Polk
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Intercession City Substation 230 kV
Data Source
LBNL
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC DeBary- Winter Springs Line
General InformationTitleInformationLicenseeDuke Energy Florida, LLCCertification # TA 92-09Date Certified05/11/1993Descriptio.
Duke Energy Florida, LLC Central Florida-Kathleen Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Duke Energy Florida, LLC DeBary- Winter Springs Line
The Florida Department of Environmental Protection is the state's lead agency for environmental management and stewardship – protecting our air, water and land.
Last updated 2026-03-14