225 MW storage in Pinellas, FL · In queue since March 2021 · Proposed COD May 2025
225 MW
Capacity
1
Components
Battery
5 years
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 2m
Suspended38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-31
Project Details
State
FL
County
Pinellas
Region
Southeast
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Bartow Plant Substation 230 kV
Data Source
LBNL